Progress as of February 28, 2006
Progress on the SkyCycle
|
The second hole is dug and rebar is tied. |
|
 |
| With forms and rebar in place, the workers begin to fill the hole with cement. |
 |
| Filling continues. |
 |
| The third hole will provide a foundation for the stairs. |
|
| Repair of a retaining wall on the banks of rhe San Antonio River, across from the H-E-B Science Treehouse, will add to the beauty of the view from the Witte backyard. The City Parks Department has crews building a barrier to keep water from the wall while repairs are made. |
 |
| Rebar is tied in place prior to building the retaining wall. |
|